Tuesday, April 04, 2017

Weekly Notes.

 Interviewed several candidates for maintenance and security positions

- Painted 605 upper and lower deck railings/painted eave area and caulked where needed/reinforced upper deck railing as it was not stable

- Painted 606 and 608 lower deck railings

- Painted the orange discoloration from the steps on the back of 600 building

- Removed weeds from the 300, 200, and 100 buildings

- Monitored the palm tree trimming

- Monitored the concrete pour under the 200 building - one more pour is needed scheduled for next week

- Monitor the rerouting of sewer pipe under 200 building by Area Foundation

- Picked up like type pool tile from Dal-Tiles in Corpus Christi

- Changed out entrance gate code and walk-through gates and emailed and texted owners and rental companies

- Changed out bulbs on the pier and crossbridge that were out

- Schedule with B&R to replace the photo cell on the 100 building as the building lights will not turn off

- Schedule with Smart Docks to start the removal of the remaining shoreguard left below water

- Verify schedule with 3G Contracting for 200 Building stucco project of April 10th - waiting for a call back

- Painted over water stains on ceiling areas in 701 near the windows


This weeks agenda
- Paint 602 and 607 upper and lower deck railing
- Paint 604, 603, 604, 606, 608 upper deck railings
- Plant new plants under the electrical panels on the 200 and 400 building
- Monitor the pool tile repair and depth markers installation with Area Foundation
- Monitor the installation of the new motor on pool pump area by Allen Pools - it rusted and went out on Friday (last install was in June of 2014)
- Touch up paint on entrance gate area
- Remove extra chain link from exit gate area
- Follow up with welder in Rockport if he is available to install bracket of pool ladder


This sewer pipe coming out of 209 was in the way for the new  foundation pier. Ralph's crew relocated the sewerline at no charge for us. 