Saturday, March 07, 2009


The dredge mix of sand and water is pumped through a tube and across Fulton Beach Road. An oversized speed hump was built and the tube is under the hump.


The retention pond didn't work very well. There were two overflow tubes to allow the water to exit the first pond and enter the secondary pool. The first time the first pool filled, the levee failed. At the point the tubes went through the first pond levee the water poured through. It can be seen in the picture at the far end of the first pond.

0 Comments: