Wednesday, September 14, 2016

Lina and Jerry had their hands full today with plumbing problems. Lina does know how to use a shovel.

Work began this week on replacing some of the stucco with hardiplank. This end of 501 shows how rotten the plywood is behind the stucco. If this project goes well, the end of 601 will be done next.

Here are some things being worked on.

- Went over with Area Foundation the confirmed start date, what parking areas is needed near the 500 building, where they are starting first - 508 side, removal of existing cardboard over sonotubes - Start date is confirmed 09/14/2016

- Obtained a list of renters/owners for the 500 building from management companies and went over the foundation project start dates and times

- Went over with Randy Edwards construction regarding the stucco project for 501 - start date is 09/13/2016 

- Scheduled quarterly pest control - 09/13/2016 at 9am

- Went over with Tony Easely regarding start date for painting of the 400 building railings - 09/12/2016 - he will be pressure washing, scraping, and sanding for the next 2 days

This weeks agenda
- Monitor the paint project with Tony Easely
- Monitor the stucco project with Randy Edwards
- Coordinate with Area Foundation Repair of where materials will be stored and start project
- Check upper and lower back deck areas for cracks in stucco