These two sections of sidewalk were completed on Tuesday. It is pretty hard to get concrete delivered. It has to come out of Ingleside and they have only one truck working this area. To get the most bang for our buck JR lined up all the concrete projects we had pending to achieve economy of scale. He hired Long Nguyen and his crew to come out to do the finish work. They did a really excellent job. These sidewalk areas had been patched a number of times, but continued to be a trip hazard as well as unsightly. When all the work was done, one half full wheelbarrow load was left. It was placed in one of the washouts on the bulkhead.