Tuesday, April 25, 2017

Lina's weekly notes

- Removed extra track from exit gate and installed on entrance gate

- Moved several pieces of shoreguard to under 100 building in lieu of 700 building because foundation contractors are working there

- Foundation contractors are under 700 building removing rotten posts

- Monitored the breakwater contractors - they came out on Tuesday 9 to 10,Wednesday 12 to (saw at 330) 5 (?)

- Removed weeds from the 200 building bayside and back of 700 building

- Pressure washed the lower back decks 701, 702, 703,704 and upper decks of 710 of 700 building - then my pressure washer hose busted

- Repaired irrigation sprinkler near entrance gate

- Hosed down front porch areas of bugs on the 100 and half of 200

- Repaired hinge on pool pump area

- Scheduled meeting with Attorney Bryan Stone on April 27 at 10:30am

- Uprooted hibiscus on the side of 701 and planted new bushes

- Painted ceiling of 201 for water marks

- Ordered the 9 volt batteries for the irrigation and smoke alarms

- Painted the gazebo posts near the 300 building

This weeks agenda and weeks forward
April 24th - Caulk above porches and corner areas 500, 600, & 700 building
                   Email policy parts that are completed
                   Pressure wash other half front porch areas from bugs of 200, 300
                   Meet with Bryan Stone - Attorney April 27th at 10:30am 
                   Order Schedule 80 posts from Fergusons to replace crossbridge poles
                   Trim bushes as needed
                    Install all-thread in west finger piers to give extra support - need to reevaluate
                   Install extra support beams on 2 finger piers behind the 400 building
                   Order irrigation controllers
                   Monitor the start of the pier turn-out project by Area Foundation

May 1st - Send out newsletter to owners
                 3G Contracting Stucco project will begin behind the 200 building
                 Caulk above porches and corner areas 100, 200, 300, 400 building
                 Improve landscaping on entryways to condos
                 Pressure wash on back decks and under upper deck - 500 building - Need to see if we can 
                 get other pressure washer going
                 Touch up paint on entrance and exit gate area
                 Pull sand away from skirting behind 100 building change out rotten skirting on the bayside

May 8th -  Replace 2 -3 crossbridge poles with Mike Rodriguez - Electrician       
                 Touch up paint on pool fence area
                 Pull sand away from skirting behind 100 building change out rotten skirting on the bayside
                 Touch up paint on gazebo posts near pool area
                 

May 15th - Purchase another BBQ from HEB
                   Order 4th garbage bin for property to be dropped off for the week of