Tuesday, October 19, 2010

The barge crew has been out working on the breakwater since last Friday. They seem to go out about an hour and then come back and leave until the next day. It's hard to tell from here what progress is being made. It appears to be about 70% repaired. In this picture you can see a long length of shoreguard being lifted in the air to be placed into the breakwater. These pieces of shoreguard are 20 feet long. The ones that failed look to be only 10 feet long. The original assessment was to repair the other side, but since then the north side has developed problems that are of higher priority to repair.
Yesterday the stucco repair on the 700 building was repainted.