Thursday, March 06, 2014


 The east-west part of the bulkhead repair is ready for concrete. It is scheduled to be delivered tomorrow. The center section will be dealt with when the other parts are completed. Notice also the kayak tethered to the bulkhead. It had been there for a couple of weeks without anyone knowing who it belonged to. Jerry moved it yesterday to a location behind the maintenance shop. Last evening the owner called out the local police because he thought it had been stolen. This illustrates again why guests need to identify their boats, trailers, and kayaks with the number of their unit.
 Jerry is working on installing another basketball backboard and post at the north end of the tennis court. He may have to relocate a couple of water lines in the process.
 Jack Gibbs operates his bobcat here to prepare for a pad for the dumpster. Tomorrow's concrete will be used on the bulkhead as well as this pad. The plan was to put two dumpsters here, but the dimensions just did not work out. The plan is to put another pad and dumpster just north of the shop area.
Chuck and Sandy(107) have been working this week to increase the size of their downstairs bathroom. They were able to sheetrock over the closet in the bedroom to increase the width of the bathroom by two feet. This allowed them to relocate the toilet. They went with a walkin shower on the right side here. They also increased the door opening from 24 inches to 30 inches. This was all possible because their electrical panel was mounted on the south end of the closet instead of the east wall like others in this building. The panel is now in the bathroom.

0 Comments:

Post a Comment

<< Home