Lina's weekly notes.
- Fixed the floor that is deteriorating in the exterior closet of 605 for closing
- Fixed the floor that is deteriorating in the exterior closet of 605 for closing
- Order the exterior closet door through Probuild for 605 and bill owner accordingly
- Caulked above bay windows and windows that needed caulking on the 200 building and painted the trim
- Stucco patched visible cracks on the 100 building
- Check and set irrigation timers on the courtyard and make sure all sprinklers are working. Also making a spreadsheet layout of the irrigation sections for each control
- Picked up the pool ladder from Leslie's Pool Supply. Asked if they had a bracket that can be purchased separately for the bottom part of the ladder to bolt into the sidewall. Going to talk with Welder - Jack about a bracket being welded on the bottom area
- Installed a new flood light under the gazebo near the 300 building as the other one corroded
- Monitor the breakwater project of Randy Edwards crew
- Forwarded B&R Electric invoices to Nick for work done on the property. They had charged us for the following:
Office Bathroom -
Electrical on the crossbridge for fixing all the lights (junction boxes under the deck areas got water in it from high tides - $293.24 (Phase II shared cost $117.30)
B&R Electric will provide us a bid to reroute the junction boxes to under the railing areas
- Monitor the 1 finger pier disassemble, lift, and reassemble project by Randy Edwards crew
- Trim palm fronds on the back of 400 building
- Discuss the revised quote with 3G Contracting for the 200 Building stucco project
- Trim the bushes in the porch areas of 400 buildings and areas by the boat parking and dumpsters
- Weed eat and pull weeds from the 100 building porch areas and curbs
This weeks agenda
- Go over with Area Foundation on the progress of 500 building being completed with brackets and bolts so that we can start straightening the skirting
- Pick up the 5 gallon paint from Sherwin Williams that matched the buildings
- Start painting the orange areas on side of buildings - 210, 201, 701, 501, 108
- Order post lantern lights for back of 400 building
- Trim palm fronds along driveway
- Spray 30 second mildew solution, scrape, and paint gazebo posts white
- Monitor the 2nd finger pier disassemble and reassemble by Randy Edwards crew
- Discuss with Area Foundation for the bulkhead design
- Install 3 smoke detectors in 202 per owners request and bill owners accordingly
0 Comments:
Post a Comment
<< Home