Friday, May 15, 2009


The replacement of the crossbridge has been completed except for the lighting. Rob will now take his barge and crew to work on replacing the end of the Phase I pier.
Concrete was poured in the parking area this morning. They have reached the area up to the maintenance shed. The last two pours have had extra calcium added to the batch to speed the drying process. This decreases the strength somewhat, but it lets cars get on the concrete in about 36 hours.
There will likely be a crowd this weekend with the Babes On The Bay fishing tournament. Large tents are set up downtown near the ski basin. There are over 800 entries this year.