Tuesday, March 07, 2017

Lina's weekly notes.

- Planted flowers under the sign at entrance

- Trimmed more palm trees along driveway

- Weed eated the curb line along the 500, 200, 300 building

- Trimmed the bushes along 500, 400, 300, 200, 100

- Requested for Tel Haley to mow the grass this week - after next week depending on what the lawn looks like, will have him start weekly mowing

- Spoke with Allen regarding the pool repairs and revising the bid for the top depth markers, rust spot on bottom, epoxy paint on step, and installing the ladder.

- I spoke with Ralph regarding the tile repair under the lip of the pool and he said he can do it along with the depth markers on the wall sides.

- I called B&R Electric for the repair of the light in the pool and he said they do not do electrical work in the pools themselves.  The pool contractor is responsible changing the light bulbs and gaskets when a light goes out.  Allen said it's an estimated $140 and will add to the revised bid.

- I spoke with our insurance carrier and asked for an extension and explained to them regarding the contractors we have out here and that Bayfront has not had these requirements in several years so they had reinstated the policy but we still have to have it done within a reasonable time.  Pictures can be sent for the progress of it.

- Spoke with OSHA regarding compliance and they said they need signatures from the employees who have reviewed the Hazard Communication Program.

- Purchased 1 BBQ, installed, and put near the pool

- Spoke with Ralph regarding foundation progress and where we are at under the 200 building - he has concrete scheduled for March 9th

This weeks agenda
- Go over with Jerry on a painting of the railing schedule for the next 2 weeks
- Go over with the employees regarding the hazard communication program
- Go over the To Do List that the Board has updated
- Forward the Compilation of Hardiboard Wall Fabrication to 3G Contractors and get their proposal turned over to a contract
- Get size and length of Schedule 80 piping to order from Fergusons for post replacement on the crossbridge
- Remove the grass from beach
- Take ladder to welder to weld bracket on bottom of pool ladder
- Assist with opening and closing of doors for quarterly pest control on March 10 at 9am and check smoke detectors